Product Description: 1. The brick wall is built with M5 cement mortar, and the inside and outside of the ground are plastered with 1:2.5 cement mortar; 2. When the bottom layer is below the groundwater level, waterproof treatment shall be done, otherwise water seepage treatment shall be done; 3. Lintel is made of 6 steel bars and 20 concrete; 4. After the processing, assembly and welding of 8# channel steel base, carry out anti-corrosion treatment (the user determines the anti-corrosion method); 5. 8. Place the foundation notch on the channel steel base and fix it with tie bars and concrete; 6. Users can not make cable wells (dotted line orbital part) according to the specific conditions of the construction site